Date
Attendees
- Craig Basl
- Derek Wilson
- Stephen Pellow
- Chris Leibfried (Customer)
Discussion items
| Time | Item | Who | Notes |
|---|---|---|---|
| 4 min | Confluence Update | Ben |
|
| 2 min | Vision/Summary | Ben, Jamie, Craig, Derek | |
| 5 min | Spiral Pump Test Plan | Ben, Craig, Derek | |
| 2 min | Spiral Pump Update | Craig, Derek | |
| 5 min | Water Hammer Test Plan | Jamie | |
| 2 min | Water Hammer Update | Jamie | |
| 5 min | Risk Tracking | Ben | Risk Management |
| 5 min | Purchasing Update | Jamie | Question: If every part on order arrived today could we start work now? |
| -- | --- | --- | --- |
| 30 min | Peer Reviews | Ben, Jamie, Craig, Derek, Coach |
Action items
- Benjamin Wilson Gantt Chart Update by
- James Haviland, Derek Wilson, Craig Basl Purchasing Retrospective for
- Re-Schedule peer reviews Benjamin Wilson