Team Vision for Detailed Design Phase

For our Detailed Design Phase, Team 19305 aimed to integrate mechanical subsystems with electrical components, complete a BOM with part numbers, quantities, and prices clearly defined, and seek additional funding opportunities. As a result, the team planned out which materials must be purchased over summer break in order to accommodate longer lead times for parts. Finally, tasks and timelines for MSD II needed to be determined.

Progress Report

Further progress has been made in developing the electrical side of the BOM, while a complete BOM for the mechanical components has been assembled.  Additional design work for the long board and for the Cam Assembly was conducted.

Drawings, Schematics, Flow Charts, Simulations 

From the foam model created for the last review the design was reworked to have truck mounts at an equivalent vertical height. Increasing the maximum internal volume while decreasing the overall length was also a priority.

Hand Sketches

Based off the new requirements these initial sketches were drawn up

Digital Sketching 

These were then measured with calipers and refined on a tablet medium. Sections where lights could eventually reside were shaded in gray and red. For the purpose of scale, wheels with fenders were drawn as well

Conversion to CAD

Finally the tablet sketches were converted into CAD and geometry adjusted to be realistic. From here the model can be refined farther for manufacture. The deck below has a 2" deck thickness, 10" width, and 44" inch length which used to be 48". A lip on the edge of the board was included for assistance in turning.

Isometric View

Right View

Front View



Full Cam Assembly V2


Hanger v2

Baseplate V2



Cam Design 

Bill of Material (BOM)

A link to the live Parts List and Bill of Materials can be found here.

Our bill of materials has three main options for construction tailored mainly around the materials used to physically fabricate the board. In summary Option A consists of materials used for building the board out of billet aluminum stock, Option B out of Delrin stock, and Option C out of a foam composite. Aluminum is a wildly expensive option without donated materials and Delrin is as well. The foam composite is much more affordable however it's a novel building method and is relatively experimental. Over the summer design will continue based on a board made of aluminum but the foam will be tested to see if it's a viable substitute down the road. 

Figure 1. Snapshot of Phase IV BOM for Electronics.


Figure 2. Snapshot of Phase IV BOM for Mechanical (Option 1).

Figure 3. Snapshot of Phase IV BOM for Mechanical (Option 2).

Figure 4. Snapshot of Phase IV BOM for Mechanical (Option 3).

Risk Assessment

Risk CategoryRiskCauseEffectRisk PreventionContingency PlanPeriod Until Switching to CPLead TimeLikelihoodSeverityImportanceOwner(s)
TechnicalFolding Mechanism RoadblockComplexity in Design and Material ScarcityCan't integrate all essential parts and can't proceed with the design.We build a functioning prototype without a folding mechanism (mule).We design a different folding mechanism into our mule based on hinges.2 weeks6 weeks9981All
TechnicalFailure of Force SensorsDamage to sensing surface or blocked transmission of force to sensing surfaceComplete loss of motor control/unexpected motor responseThoroughly test force sensor installationUse remote to control motors2 weeks6 weeks3927Matthew G.
SafetyMotor failureLow resistance and Electrical overloadCorrosion of the motor shafts, bearings, and rotorsDetermine the full specifications for what type of motor we are looking forInvest in a High quality motor2 weeks6 weeks3927Deirdre A. Matthew G.
SafetyStability failureTrucks don't work as designedDanger to the rider of falling and hurting themselvesConduct tests of trucks over full range of speeds with differing loadsFind trucks that are stable2 weeks6 weeks3927Tanvir M. Connor F.
ResourceNot Being Able to Design PCB BoardLack of experience with PCB design.Non-functioning PCB.Try to find a professor to help verify.Buy VESC.2 weeks6 weeks3927Matthew G
TechnicalProduct failure or part malfunctionsMiscalculations during design processA non-functioning productMechanical Design Leads must be consulting each otherConsult with Mechanical Engineering Professor.2 weeksN/A3927Tanvir M. Connor F. Erik L.
TechnicalControl system causing unexpected outputs (malfunction)Incorrect inputs were put in the systemIncorrect Outputs/System FailureHave at least one other team member monitoring the inputs made to the systemHave a micro-controller system expert look over the system3 weeksN/A199Matthew G.
TechnicalElectronic components protectionExposure to external environmental factors (water,rocks, etc.)Damage to the battery and other componentsEnsure proper location and protection of electrical components.Have a guide for a particular environment that must3 weeksN/A133Kristin O.
SafetyPinch points in the mechanismFolding MechanismDamage to hands and fingers of riders.Proper outlined guide for Hand PlacementWear protection gloves3 weeksN/A133Tanvir M. Connor F. Erik L.
SafetyOverall integrity of collapsible partsWeak focal pointCollapsible mechanism does not have a long life span and the board is damaged after few usesDetermine the best and most applicable collapsible mechanism.Hinge system3 weeksN/A199Tanvir M. Connor F. Erik L.
ResourceLack of additional funding (Budget)Not keeping track of spendingUnable to finish design or a low quality productProper documentation of spendingCut costs where necessary3 weeksN/A339Deirdre A.
ResourceCustomer manufacturer quality and accuracy riskBad quality deliverLow quality productMake sure to order from reputable manufacturers.Change suppliers3 weeks6 weeks199All
ResourceLack of experienced riders to test prototypes or data collectionLack of exposure to longboard ridingLack of essential knowledge on the design of the longboardHave a team meeting for instruction on how to ride the longboardInterview experienced riders3 weeksN/A111Erik L.
ResourceTeam Members Being AbsentExceptional Circumstances (Sickness, etc.)Falling behind on deadlines and not being able to create longboard.Make sure at least one person on the team has a good understanding of what the abstentee was doing,Assign the another person the absentee's task depending on how important the task is.3 weeksN/A339All

Design Review Materials

Presentation Link: https://docs.google.com/presentation/d/1UF7ItJCJz0xoMxX7isdAEeH0Supb05U_DAbMbAtKFOk/edit

Plans for next phase

The plans for our summer and next phase are displayed in Wrike here


  • Aucune étiquette