Team Vision for Build & Test Prep Phase

Summarize:

  • Plan:
    • Review and update test plans
    • Review and update risk management
    • Finalize BOM
  • Accomplishments:
    • Updated test plans
    • Update risk management
    • Updated BOM with more complete information

Test Plan Summary

Requirements and Testing Document: https://docs.google.com/spreadsheets/d/1_IZcNNnW0dwpgoJAZ-F0mmnLqIqh75EQA9Q7DGl4pTg/edit#gid=2094414087

Test Plans

TestOwnerDescriptionFileHelpful Documents
P1AllisonAC/DC Converter Output Test

P2AllisonMotor DC/DC Converter Output Test

P3AllisonServo DC/DC Converter Output Test

P4AllisonPower System Integration Test

M1Josh

Motor step distances


M2Josh

Motor supports proper weight


U1AndrewSupports 1 Monitor


U2AndrewMaximum distance of bluetooth connection


U3AndrewInput Delay


U4AndrewResponds direct input


U5AndrewTactile inputs


U6AndrewStudent input power duration


U7Andrewcan fit on wheelchair table


Risk and Problem Tracking

Risk Tracking


Problem Tracking

No problems have arisen yet.

Design Review Materials

Build and Test Prep Design Review Notes

  • Pre-reads
  • Notes from review
  • Action Items

Plans for next phase

Team Plan

  • As a team, where do you want to be in at your next review?
    • All subsystem components are ordered
    • Start subsystem tests
    • User Interface Subsystem
      • Buttons can be read
      • Have UI designed
      • Joystick can be read
    • Control Subsystem
      • Move motors specific amount
      • Move Servos
    • Motor Subsystem
      • Have motors moving
    • Mechanical Subsystem
      • Have all parts
      • Parts assembled
    • Power Subsystem
      • power tests
      • obtain all parts
    • Belt Subsystem
      • have all parts
      • test motors with belts to determine step distance
      • test motors with belts to determine if second belt is needed
    • Gripper Subsystem
      • Pick objects up
      • cup printed
      • have gripper printed

Individual Plans

  • Aucune étiquette