This wiki space may not be shared with the general publicThis wiki space may be shared with future RIT students and faculty working on follow-on projects


Project Summary

Project Information

Cryogenic cooling below 1 K requires special devices that use thermodynamic cycles that cannot operate at room temperature. In order to keep these devices cool, an adiabatic demagnetization refrigerator (ADR) is used. The ADR is composed of a solid salt crystal and a strong magnetic field. If the strength of the field is decreased, the thermal motion of the molecules twists them out of alignment. The thermal energy is transformed into magnetic energy, cooling the salt pill. When the ADR is combined with a cryostat filled with liquid helium, the device can go down to almost 0 K. This heat switch must cool the detector and then mechanically disconnect before flight. A prototype was previously designed and nearly ready for testing but was not completed due to COVID-19 shutting down the cryogenics lab.

The goals of this project are to iterate the design of the previous team’s prototype and identify opportunities to incorporate a mechanical actuation heat switch that will disconnect before flight. The expected end result is a functional and tested prototype that will thermally disconnect the ADR from the bath to allow the thermodynamic cycle to proceed before flight. The resulting design and prototype must fit and operate in an existing cylindrical envelope of a rocket payload and the Center for Detector’s (CfD) cryostat. In addition to this the prototype must be non-magnetic, able to endure temperatures of 77 K while testing, 4 K in flight, and operate in a vacuum. The prototype must be well designed, undergoing 1,000 operation cycles and sustaining the simulated vibrations that occur in a rocket launch. Four manuals must also be produced including how to train operators, maintain the device, service the device, and for flight operations.   

The finished prototype operated well and cryogenic temperatures and passed all vibration testing. Work needs to be completed to improve the heat transfer rate to meet customer requirements. New arms have been designed and will be handed off to the customer. These new arms are expected to increase the heat transfer rate from the original arms. The 1,000 lifetime cycle test was stopped prematurely due to a flex pivot failure. This occurred about 150 actuations in and the team felt comfortable this specification would have been met without the failure. Fortunately the flex pivots would have had to been replaced anyway for the new arms. The new arms should complete this prototype and improve its ability.

Project Title: Flight-Ready Heat Switch for Deep Cryogenic Applications

Project Number: P21129

Project Family: Heat Switch

Start Term: 2201 Fall Semester 2020

End Term: 2205 Spring Semester 2021

Faculty Guide: William Nowak

Primary Customer: Dr. Mike Zemcov

Sponsor (financial support): Center for Detectors

Team Members

Pictured right to left: Chris Witmer, Maxwell Williams, Cameron Collins, Matt Blanc, Chris Alexander, Matt Chuttey

MemberMajorRoleContact
Chris AlexanderIndustrial and Systems Engineering

Project Manager

email
Matt BlancElectrical Engineering

EE Lead

email
Matt ChutteyMechanical Engineering

Team Facilitator

email
Cameron CollinsMechanical Engineering

Systems Engineer

email

Maxwell Williams

Mechanical Engineering

Purchasing

email
Chris WitmerMechanical EngineeringSystems Engineeremail


Work Breakdown: By Phase

Work Breakdown: By Topic

Acknowledgements

  • We would like to acknowledge Dr. Zemcov for his passion, dedication, and support in completing this project
  • We would also like to acknowledge our guide William Nowak and the projects previous guide; Marty Pepe, for their guidance in navigating this tricky subject
  • The Center for Detectors for financially supporting this project
  • Dr. Anselm for his facilities and willingness to help
  • Dale Mercado and Serena Tramm for their help in prepping and conducting tests




  • Aucune étiquette