Date 11/23/20

Presentation

Attendees

  • Cody Beckwith

  • Nils Aldeborgh
  • Justin Ross
  • Dan Murphy
  • Erich Gauss
  • Kenny Cirigliano
  • Jerry Adamski
  • Joel Rosen
  • Stephen Jacobs

Goals

  • Update stakeholder's on current issues
  • Confirm ER's and CR's
  • Obtain approval to move forward with the project

Agenda and discussion notes

TimeItemWhoNotes
1 min  Cover SlideDan
1 min FacesDan
1 minVision for PhaseDan
1 minAgendaDan
3 minAction ItemsJustin
1 minNew Product Development ProcessErich
1 minDetailed Design DeliverablesErich
1 minCustomer RequirementsCody
1 minEngineering RequirementsCody
2 minDesign Drawings,...Nils
2 minBill of MaterialsKenny/Nils


1 minTest PlansCody
1 minRisk AssessmentNils
1 min

Contingency Plan

Nils
1 minNext StepJustin
1 minPlans for Build & Test Prep PhaseJustin
1 minNext Phase Gantt ChartJustin
1 minJustin, Dan, Kenny 3-wk plan

1 minCody, Nils, Erich 3-wk plan

Issues Raised

  • missing design and flowchart section in confluence
  • Cody will be in contact with stakeholders regarding the raspberry pi over break
  • Take home things to work on over break if possible

Decisions Made

  • Professor Jacobs has authorized that he will purchase the LEDs, freeing up budget for other things

Action items

  • Set up gate review
  • Complete a peer evaluation after your review. Recommended template is here
  • Add design and flowcharts section to confluence page