Date: 10/28/20

Slide Show

Attendees

  • Cody Beckwith

  • Nils Aldeborgh
  • Justin Ross
  • Dan Murphy
  • Erich Gauss
  • Kenny Cirigliano
  • Jerry Adamski
  • Joel Rosen
  • Stephen Jacobs

Goals

  • Update stakeholder's on current issues
  • Confirm ER's and CR's
  • Obtain approval to move forward with the project

Agenda and discussion notes

TimeItemWhoNotes
1 min  Cover SlideDan
1 min FacesDan
1 minVision for PhaseDan
1 minAgendaDan
3 minAction ItemsJustin
1 minNew Product Development ProcessErich
1 minPreliminary Detailed Design DeliverablesErich-Add check marks to all completed tasks
1 minCustomer RequirementsCody
1 minEngineering RequirementsCody
1 minRisk AssessmentNils
1 minFeasibilityNils
2 minBill of MaterialsKenny/Nils

-ONE SPARE OF EVERYTHING

-ADD LED STRIP

-Look to buy tempered glass locally to avoid delivery complications (Mr. Glass)

1 minGame ControlCody
1 minPlayfield Simulation AdjustmentCody-USE RUBBER BAND TO ELIMINATE SLOWDOWN POINT
1 minProblem SolvingErich
1 minNext StepNils
1 minPlans for Detailed Design PhaseNils
1 minNext Phase Gantt Chart

Justin


1 minJustin, Dan, Kenny 3-wk planJustin, Dan, Kenny
1 minCody, Nils, Erich 3-wk planCody, Nils, Erich

Issues Raised

  • Complete test plans
  • Waiting on finalized top cabinet design from Prof. Jacobs
  • When preparing for break, organize team resources in a way that it could be picked up by another team to continue in the future.

Decisions Made

  • Purchase one extra of everything
  • Look into buying tempered glass local
  • Listing all decisions where team, guide, and client can see them helps keep everyone on the same page.

Action items

  • Send visual pinball files to Prof. Rosen and Prof. Jacobs
  • Supply wood to Prof. Rosen for paint/print testing
  • Give Prof. Jacobs his video camera
  • Get LCD Dimension's