Team Vision for Build & Test Prep Phase

Summarize:

  • What did your team plan to do during this phase?
    • Our team planned to receive orders and inventory them.  We then planned to come up with a more detailed plan for the coming phases.  

  • What did your team actually accomplish during this phase?
    • Our team inventoried our many purchase orders, and determined what was missing.  We ordered more parts based off of research.  We talked with Gary about our design, and received feedback that will require redesign and further purchasing.  

Inventory

Electrical BOM

A large majority of the parts needed for the electrical subsystem have been received. A few recent purchases constitute the orange region. All parts are expected to be received within the course of a week or two.  

Mechanical BOM

The mechanical BOM has all parts required to start manufacturing as of last phase. With new changes being implemented, the mechanical BOM will be updated to reflected the changes made. 

Test Plan Summary

Engineering RequirementImportanceSourceNameMethodUnitsLowest ValueIdeal ValueMax ValueTest Plan
4MediumCR1, CR8Switching TestElectrical TestTime (ms)00201
11MediumCR 1Power TestPowerW1203005002
1,2,15,16MediumCR9, CR12Tilt TestDegree of TippingDegrees510203
9MediumCR10, CR11Module Pick Up and MoveManual LiftPounds3040504
6MediumCR9StandingObservationBinaryFailPassPass5
7MediumCR6, CR3Assembly From PackagingTime StudyTime1015306
8MediumCR6, CR4Assembly From TransportTime StudyTime35107
17MediumCR2, CR9Physical Load TestApplying LoadsPounds501002008
5MediumCR12Vibratory TestModelingBinaryFailPassPass9
10MediumCR11Sizing TestModelingBinaryFailPassPass10
13MediumCR9, CR16Weatherproofing TestWater SprayStandardsIP12IP23IP2311
18MediumCR19Modular, Replaceable PartsPhysical TestingTime10152012

Our team has the space required to start the electrical testing, rows 1 and 2. The rest of the tests require the cart to be fully assembled.

Budget


Risk and Problem Tracking

Risks

One risk was modified, 9, and one risk was added, 35. These changes can be seen below and the rest of the risks in the following document: Updated Risks MSD II .


The risk of us going over budget was lowered to a 1  for likelihood and a 1 for severity.  We have all of our parts ordered and the required design changes are projected to only be around $20. We added a risk for deliverables being too late. This was added to account for any delays we may experience due to required design changes. This is a 3 likelihood, since redesigns were required, and a 1 severity because they should not set us back too much. 

Problem Tracking

The only problem that requires corrective action at this point is a re-design of some of the welded assemblies that need some changes to make them easier to fabricate.  


Problem Tracking Live Document

The re-design will change the upper assembly of the scissor module to be welded in sections. The sections highlighted in the same color below will be welded (if there are multiple connected parts in the section) and then those sections will be bolted to each other instead of the entire assembly being welded.

Design Review Materials

Include links to:

Plans for next phase

  • As a team, where do you want to be in three weeks at your next review?
    • As a team we hope to have a working solar module subsystem.  With this finished system we will be able to carry out test plans for power switching.  While we are doing this, hopefully the machine shop will be processing our materials for the other subassemblies.  

Garrett's Three Week Plan

Jake's Three Week Plan

Matt's Three Week Plan

Christian's Three Week Plan


  • Aucune étiquette