Date: 11/23/20
Attendees
Customers: Marcos Esterman and Alvaro Rojas
Guide: Jennifer Indovina
- Team: Jacob Wildt, Matthew Madsen, Christian Niebling, Garrett Waldron
Goals
- To show progress made towards final design including full system and subsystem prototyping, feasibility analyses, schematics, and CAD models.
- Confirmed with customers that our vision for the project is aligned with theirs.
- Add further detail to our final design drawings.
- Develop a package of test plans.
Agenda and discussion notes
| Time | Item | Who | Notes |
|---|---|---|---|
| 45 min | Gave Detailed Design Presentation | All | Presented our Phase 4 PowerPoint |
| 20 min | Discussed Questions Regarding the Presentation | All | Had answers to most questions and left the review with confidence in the work completed. |
Issues Raised
- CAD documentation was missing dimensions in our review.
- Large size of electrical box.
Decisions Made
- Add CAD drawing dimensions and show on confluence.
- Look into size of electrical box
Action items
- Complete a peer evaluation after your review.
- Post meeting notes document to each phase. Link: Phase 4 Review Notes
- Add CAD drawing dimensions.