Intellectual Property Considerations

Our team plans to address any IP considerations by making an agreement to discuss any transfers of IP ownership before making them.

Team Setup

Our Guide: Jennifer Indovina 

Team Values and Norms

ProjectP21462
TeamSparkCart
OwnerMatthew Madsen
Date9/7/2020
Team Norms
  • Thorough
    • Effort is evident in any submitted work
    • All work is done with the objective of making the project better
  • Punctual
    • Be prepared for the presentation prior to the start time
    • Show up to the meetings on time; if you will be late, communicate that
  • Professional
    • Communicate through slack
      • Check notifications regularly
    • Give credit where it is due
    • Communicate any foreseeable problems in advance
    • Be respectful to all parties
    • Dress accordingly for meetings


Project Plans & Schedules

Our project uses Microsoft Project for scheduling and task tracking.  Microsoft Project uses task duration and dependencies in order to create a Gantt chart to exhibit the project's critical path, and also make the team aware of the tasks at hand.  Here is an example of our phase 1 Gantt chart.

Owner: Jacob Wildt


This document is a constant work in progress to keep our team on track.  A live link to our project's current master schedule can be found here: https://drive.google.com/drive/u/0/folders/1Aegtu-n_3FbTM__ySeaBh9-b_0BiLCWx

Risk Assessment and Growth Curves

IDCategoryRisk ItemEffectCauseLikelihoodSeverityImportanceAction to Minimize RiskOwner
1SocialCovid related university shutdownCan't build actual prototypes and do testingNot being on campus224Online analysis and "build"All
2SocialThe cart is too expensive for commercializationWon't be viable for target consumerThey lack funding212Design with this in mindJake
3EnvironmentalDo not fully understand the environment our cart will be placed inMay not design for all terrainNot being completely informed of terrain122Having a continual discussions with AlvaroJake
4EnvironmentalThe solar panels are vulnerable and break in transit or transportationThe main renewable energy source is compromisedRough handling during transit or accidents122Make sure the panels are stored safely in the final designMatt
5ResourceLack of a CELack of user interfaceLess informative cart300Christian will code when neededChristian
6ResourceIt will be hard to replace broken parts locallyHard to fix broken partsFew resources available to fix cart133Design with this in mindGarrett
7ResourceInability to access labsUnable to testCovid-19 restrictions224Test whenever we are ableAll
8ResourceIf lots of changes are necessary, we may not be successfulUnable to complete designDesign work from previous team133Gain full understanding of existing design early onGarrett/Christian/Matt
9ResourceWill we have enough funding to make our future design changesMay have to cut some design cornersDesign becoming to expensive111Paying close attention to our $1500 budgetAll
10Technical / ResourcePreviously purchased equipment not functioning properly in assemblyFurther Purchasing will be requiredPoor Design212Use care when handling equipmentAll
11TechnicalPoor analysis from the previous team affected designRedesigns would be necessaryAnalysis is incorrect which affects design decisions224Redo previous analysisMatt
12TechnicalThe cart will not function reliablyCart will not function when neededUnreliable components236Source components with this in mindAll
13TechnicalOur system may not be efficient enough for the necessary outputNot enough power for printerPoor efficiency122Get as much info on components as possible pre-purchaseChristian
14TechnicalThe cart may not be durable enoughCart is susceptible to damagePortability, size, and weight constraints236Test cart shell without components in dangerGarrett
15TechnicalThe switching of the power sources is not seamless and has to be redesignedThe cart preventing grid failures requirement is not metPoor electrical design030Research tolerances appliances can handle from an outletChristian
16TechnicalThe electronics will not have adequate coolingThe cart cannot supply power from instrumentation failureLow inverter efficiency, poor airflow/cooling236Look at requirements for water resistance and if airflow can be introducedChristian
17TechnicalThe cart becomes too heavy with equipment, our goal of mobility is not metUnable to transport effectivelyHeavy batteries/components, cart is not collapsible133Design with this in mindGarrett/Matt
18TechnicalThe electronics interfere with each other; Backflow of currentElectronics fail during useBad electrical design122Ask subject matter expertsChristian
19TechnicalCart collapsing mechanism does not work properlyTransport is inhibitedBad design133Make sure design will be compatible with size restraintsGarrett/Matt
20TechnicalInsufficient power for cart applicationCart cannot perform off-grid electrical dutiesSub systems are inefficient, power production is low, battery capacity is too small111Design with power requirements in mindChristian/Matt
21TechnicalCommunication to the charge controller is too difficult to completeThe arduino/display subsystem is inoperableNot sufficient knowledge with modbus protocol20.51Learn modbus protocol and conduct testing earlyChristian
22TechnicalAll equipment does not fit in the cartUnable to transport effectivelyAdditional power sources are too large122Look at dimensions before incorporating to our designGarrett
23TechnicalCart does not reach adequate working heightWorkstation uncomfortableDesign Flaws111Be thorough in design planningGarrett / Matt
24TechnicalCart requires two people for setupCart unable to be setup by one personDesign Flaws20.51Design accordinglyGarrett / Matt
25TechnicalScissor lift technology is not effectiveWill have to go with telescoping, less collapsibleWeight / Material restrictions111Ensure materials are availableGarrett
26TechnicalUnable to use modular design due to electronic wiring restrictionsWill need to remake design planComplex wiring connectors not usable133Plan wiring extensivelyChristian
27TechnicalSolar Panels don't have good enough support and break during foldingNeed to redesign modulePoor material selection111Do proper researchGarrett / Matt
28TechnicalProject Plan not communicated well enoughDeliverables may be latePoor Management111Stay on top of schedulingJake
29TechnicalWork space is not an adequate sizeCramped workstationDesign Flaws111Design accordinglyMatt
30TechnicalOvercharging & deep discharge of the batteryDecreases battery life and efficiencyDesign Flaws111Design circuit accordinglyChristian
31TechnicalChoosing a non adequate roller and track systemRedesigns and purchasing would be necessaryDesign Flaws122Conduct thorough analysisGarrett / Matt
32TechnicalChoosing a non adequate hinge system for solar panel foldingRedesigns and purchasing would be necessaryDesign Flaws122Conduct thorough analysisGarrett / Matt
33SocialConflicting customer ideasRedesignsMiscommunication212Communicate regularlyJake
34SocialCart not effectively educating the userRedesigns and further cart improvements will be necessaryDesign Flaws122Do proper research and redesign the sub-systemsJake / Christian

Risk management as of 11/23/2020

Meeting Minutes, Notes, & Actions

This information can be found under Meeting Notes.

Peer Reviews

Problem Definition Peer Review

Project - P21462

Team Name - Solar Powered, Portable 3D Power Cart v2

Document Owner - Jacob Wildt

Date - 9/7/2020


Jacob WildtChristian NieblingMatthew MadsenGarrett Waldron
Overall team member performance against team's values and norms.



One strength



One area for improvement



1 - Poor, 2 - Needs improvement, 3 - Performs as expected, 4 - Above the level of the rest of the team, 5 - Outstanding


Communication

Christian Niebling is the communicator and point of contact for our team

  • E-mail will be the primary method of contact with our customer
    • Dr. Marcos Esterman is our customer in Rochester.
    • Dr. Alvaro Rojas Arciniegas is our customer in Columbia.
    • The frequency of contact will be dependent on the project cycle.
    • At least 24 hours before project reviews, an e-mail with meeting details & pre-read documentation will be provided.
    • All team members will be CC'd on customer communication e-mails.
  • Within team communications
    • Our team's main method of communication will be Slack.
    • We will notify our guide whenever we are planning meetings in Slack.
    • Due to the small size of our team, we will use our main Slack channel for most discussions, with the others taking place in direct messages between members.

Project Reviews

Design Review Notes

Gate Reviews

  • Aucune étiquette