Your team will hold a gate review with your guide at the end of each semester. This page should document any information needed for the review, as well as outcomes.

MSD I: Reflection and Readiness for MSD II Work

  • Use this space to organize information for your review. Key elements are listed here
  • Your team should complete a self-critique and report the results here.
  • Note: lack of readiness means your team will have a critical design review at the end of the first phase of MSD II. This is typically a result of significant unanswered feasibility questions with no clear path to solution. 

Expectations

  • All team members present and prepared to report on team and individual status.
  • All team MSD deliverables are complete and uploaded, and ready to be graded.
  • Guide is present and prepared to evaluate all items included in the review.
  • Review should take about an hour.

Status Review

Current state of the project

  • Summarize expected performance vs. requirements (include snapshot of current requirements document here, along with a link to the live document.)
  • Address any issues raised during your Detailed Design Review. These will generally fall into one of three categories
    • Issues that have been addressed and the team is closing them out. (GREEN, team is ready to proceed to build and test)
    • Issues that have not been addressed yet, but the team has a clear path to a solution. (YELLOW, team expects to be ready for build and test, and a Critical Design Review may be held in MSD II Week 2)
    • Issues where the team has not been able to identify a solution or a clear path to a solution. (RED, team is not ready for build and test, and a Critical Design Review will be held in MSD II Week 2)
  • Compare your current project plan/schedule to your original plan/schedule.
    • Has the scope of your project changed?
    • How and why did your schedule change?
    • What have you learned from these changes?

The team decided that a on-demand concrete mixing system would be out of the scope of this project. Feasibility testing proved that such a subsystem would take too much time and development to allow for the successful completion of all the other subsystems. This pushed our schedule back about 3 weeks, which we think we can makeup during the Winter break. From this setback we learned we need to be very realistic in what we pursue and do a better job of developing subsystems in parallel. It is easy to get caught up in the testing of a particular subsystem but owners of other subsystems must make sure they are still keeping their work on track despite any additional workload that may come from testing.

  • Review individual team member status.
    • Did you deliver on your personal responsibilities?
    • Did you use your MSD I plan effectively? Was it realistic? If not already addressed above, what did you learn from this and how have you applied this toward a meaningful and realistic MSD II plan?

Our original MSD I plan wasn't very realistic. Unfortunately we probably bit off more than we could chew by adding additional subsystems and functionality to the design, while understating how much work it would be to get the base subsystems working. So our initial scope was too large for the size of our team. We don't think this was all a waste though, as we uncovered some interesting future work that could be done for the printer. Specifically an on-demand mixing system certainly isn't outside the realm of possibility but would require more work than we can give it at this time. To make MSD II successful we have narrowed our scope and removed some subsystems from our design.

  • Compare your current risk assessment to your original.
    • Have you closed out your most important risks?
    • Do you have remediation plans for remaining risks?
    • Have any of these risks manifested themselves as problems?
    • How did your risk assessment change? What can you learn from this?

Review your team's MSD II schedule (if not done during DDR)

  • Your schedule demonstrates that you can deliver a functional prototype to your customer by your final phase demo.
  • Your schedule incorporates lessons learned from your MSD I reflection.
  • Spring-finish teams should include a vision for their Imagine RIT exhibit.
  • Plans for Break

    Task Description

    Start by

    Duration

    Complete by

    Sequence

    Impact

    Time Required

    Member

    Duet configuration file

    12/153 weeks1/20After gate reviewAllows the Duet to work with our motion system

    6 hours

    Anthony

    Code for motion control12/213 weeks1/20After gate reviewInterfacing between Duet and linear rails10 hoursAnthony
    Calibration system design1/22 weeks1/15After MSD II startsCalibrating the printer on every start up is required10 hoursAnthony
    Contact stepper motor suppliers for torque curves12/51.5 weeks12/15After stepper motor testingNecessary information for the stepper motor selection2 hours + response timeDerek
    Finalize stepper motor selection for Extruder12/150.5 weeks12/19Need more information on stepper motors to make the selectionIs necessary for an extruder design that can reliable extrude concrete3 hoursDerek
    Order stepper motor12/194 weeks1/9Need the stepper motor before the extruder mount can be designedThis will determine the final dimensions/weight of the extruder1 hour + delivery timeDerek/Nico
    Finalize stepper motor mounting design1/091.5 weeks1/20This will be a critical portion of the final designThis will determine the final dimensions/weight of the extruder3 hoursDerek
    Redesign internal bearings of extruder12/104 weeks1/7Needs to be worked in parallel to the augerIs necessary for an extruder design that can reliable extrude concrete6 hoursDerek
    Update extruder auger design to be more efficient12/104 weeks1/7Needs to be worked in parallel to the bearing designIs necessary for an extruder design that can reliable extrude concrete6 hoursDerek
    Update the nozzle design to be modular1/73 weeks1/21Needs to be designed post completion of the auger and bearing updateIs necessary for an extruder design that can reliable extrude concrete6 hoursDerek
    Design Bed attachment system12/81 week12/15After gate reviewAllows bed to be level with extruder3 hoursTyler
    Create CAD for design12/82 weeks12/22After gate reviewFinalizes BOM for frame12 hoursTyler
    Create BOM and purchase parts12/151 week12/29After CAD completionGets parts delivered2 hoursTyler
    Parts shipping12/203 weeks1/25After parts purchasingDelivery time3 weeksTyler
    Frame assembly1/41 week1/25After parts arriveAllows for testing, not required to be done over break1 weekTyler
    Check Lowes Inventory Status of Sakrete Type S12/91 day12/30After gate reviewIf product is hard to obtain material, team will have to focus on Type N as the final option1 hourMeghan
    Keep Gantt Chart updated12/86 weeks1/25This effort will continue throughout breakEnsure team visibility of status of tasks for each member6 hoursMeghan
    Keep any test plans executed are uniformly documented and recorded in test plan file12/86 weeks1/25Complete as new tests and data are developed.Provides team and stakeholders visibility of the test plans10 hoursMeghan
    Perform gravity concrete flow testing1/91 week1/16After test parts arriveTests feasibility of a gravity fed system from reservoir to extruder6 hoursMeghan
    Conduct Tubing Crush and Bend Radius Testing12/14/20202 weeks12/28/2020After Gate ReviewThis will determine the tubing material selection for the peristaltic pump allowing for preliminary design to be completed10 hoursNicola
    Finalize Preliminary Pump Design12/14/202012/2701/05/2020After Tubing TestingAllow for a manufacturing strategy to be created and begun15 hoursNicola
    Test Pump with waterOnce parts are acquired1 weekStart of MSD IIAfter Pump Design is finalizedBetter understand how pump functions10 hoursNicola
    Design Hopper12/28/20203 weeks1/14/2020Once tubing material for pump is selectedA Reservoir system to store mixed concrete prior to printer using is necessary for the functioning of the printer15 hoursNicola
    Order Pump Materials12/2720201 week1/20/2020Once preliminary design is completeAllow for system testing at the beginning of MSD II2 hoursNicola
    Order Hopper Materials1/14/20201 week1/20/2020After Preliminary design is completeAllow for system testing at the beginning of MSD II2 hours

    Nicola

    Publish Hopper Drawings1/14/20211 week01/25/2021Once preliminary design is completeAllow for a manufacturing strategy to be created and begun5 hoursNicola
    Manufacture HopperOnce Drawing are complete1 week02/01/2021Once Drawings are complete and material is recievedAllow for system testing at the beginning of MSD II15 hoursNicola
    Manufacture PumpOnce Drawing are complete1 week02/01/2021Once Drawings are complete and material is recievedAllow for system testing at the beginning of MSD II15 hoursNicola
    Research Duet Firmware (Reprap) and Gcode12/95 weeks1/20Needed for next phaseWill give the team the knowledge needed to program the printer5 hours eachEveryone


    Plans for Next Phase

    Between now and the end of the semester the team hopes to complete the peristaltic pump design as well as finalize some bills of materials. We do not expect to do much more testing or prototyping for the rest of the semester. In order to prepare for MSD II some subsystems will be worked on over the 6 week winter break. Anthony will be working on the electrical subsystem. As mentioned before, the Duet needs custom configuration files for the connected motors and since we will be having a new extruder stepper motor, we will need new configuration files. In addition, certain minor subsystems such as the user interface and the calibration system can also begin to get designed since we now have a good idea of the direction we are going with the project. Wiring diagrams can also begin to be drawn up but subject to change; they will not be needed until the frame is assembled. Any related code will be researched and by the start of next semester we will have a solid understanding of the scope of the Duet within this project.


    As a team, we would like to be prepared for the start of the spring semester term. This includes preparation for MSD II and any left over tasks from MSD I. Below are individual tasks the team will work on to help our team achieve these goals.

    Task Description

    Start by

    Duration

    Complete by

    Sequence

    Impact

    Time Required

    Member

    Task Description

    Start by

    Duration

    Complete by

    Sequence

    Impact

    Time Required

    Member

    Wiring diagrams

    FebruaryAfter MSD II starts and frame is set upConnects everything to the Duet5 hoursAnthony
    Calibration system design

    FebruaryAfter MSD II startsCalibrating the printer on every start up is required2 hrs/weekAnthony
    User interface system

    FebruaryAfter MSD II startsProvides information to user5 hoursAnthony
    Determine extrusion rate and linear speed of extruder1/251 week2/1After MSD II starts and extruder design is completeThis will be necessary to define printing parameters and extruder capabilities4 hoursDerek
    Test extruder on the printer frame2/12 weeks2/14XY frame and extruder needs to be completeThis is a critical step in implementing this subsystem into the printer4 hoursDerek
    Test Pump and hopper together with concrete02/01/20211 week02/08/2021After parts are manufacturedEnsure pump functions as expected and any minor tweaks that need to be made can be made8 hoursNicola
    Calibrate pump rate with extrusion rate02/08/20214 days02/11/2020Once pump and hopper are tested together and extrusion rate is better understoodAllow for pump to be properly integrated with full system8 hoursNicola
    Test Hopper, Pump, and extruder together02/12/20211 week02/19/2021Once Pump is calibrated to extruder and software to control pump is writtenChecks the three systems together before adding in the variable of motion8 hoursNicola
    Test Hopper, Pump, extruder, and linear motion together02/20/20211 week02/27/2021once pump is tested with the extruderTests that all systems are working in tandem8 hoursNicola
    Revise test plans from decisions made over break

    First Class BackAfter work designated for break is completeThese may need updated dependent of the individual task completed over break.1 hourMeghan
    Update Risk Assessment Status

    End of Phase 5After Risks are raised or mitigatedRising risks must be addressed as a team and documented the corrective action taken.3 hoursMeghan
    Collect data for benchmark testing

    End of Phase 5Once design is finalizedThis will provide a benchmark for the expected and desired engineering requirements to me tested against.20 hoursEveryone
    Assemble frame

    FebruaryOnce parts come inAllows testing of XYZ axis and integration of other subsystems2 hoursTyler
    Test X, Y, Z motion

    February 14thAfter frame is assembledCompletes engineering requirement4 hoursTyler, Anthony
    Monitor for wear

    End of projectAfter frame is assembledEnsure design is rigid and rugged enough for continued useContinuousTyler
    Assist in design and assembly where needed

    End of projectAfter frame is mostly finishedSince the frame is mostly done I am more free to assist in other topic and setupContinuousTyler

Team Self-Critique

 

Deliverables Checklist and Website Status

  • All documents must be uploaded to your website in advance of the Gate Review.
  • The team should not use gate review time to conduct a detailed examination of specific deliverables unless related to discussion items in the status review.

MSD II: Project close-out

  • Use this space to organize information for your review. Key elements are listed here

Expectations

  • All team members present and prepared to report on team and individual status.
  • All team MSD deliverables are complete and uploaded, and ready to be graded.
  • Guide is present and prepared to evaluate all items included in the review.
  • Review should take about an hour.

Status Review

Current state of the project

  • Summarize actual performance vs. requirements (include snapshot of current requirements document here, along with a link to the live document.).
    • Which requirements were unmet, and why?
    • How robust is your final design?
    • Did you meet your project budget?
    • What was your customer's assessment of the work you delivered to them? Were they satisfied?
  • Compare your current project plan/schedule to your original plan/schedule.
    • Did the scope of your project change during MSD II?
    • How and why did your schedule change during MSD II?
    • What have you learned from these changes that you can apply to future projects?
  • Review individual team member status.
    • Did you deliver on your personal responsibilities?
    • Did you use your MSD II plan effectively? Was it realistic? If not already addressed above, what did you learn from this and how can you apply it to future projects?
  • Review your current risk assessment and problem solving status.
    • Have you closed out your most important risks?
    • Were there risks that you did not anticipate? If so, what do you think the reason is?
    • Did any anticipated risks manifest themselves as problems?
    • How did you use your problem solving process during the semester?

Deliverables Checklist and Website Status

  • All documents must be uploaded to your website in advance of the Gate Review.
  • The team should not use gate review time to conduct a detailed examination of specific deliverables unless related to discussion items in the status review.
  • Is prototype hand-off complete, is the team's workspace cleaned up, and have all tools been returned?

Lessons learned, etc.

  • Does the team have any other lessons learned that were not addressed above?
  • What advice would you give to future teams?
  • Aucune étiquette