Your team will hold a gate review with your guide at the end of each semester. This page should document any information needed for the review, as well as outcomes.
MSD I: Reflection and Readiness for MSD II Work
- Use this space to organize information for your review. Key elements are listed here
- Your team should complete a self-critique and report the results here.
- Note: lack of readiness means your team will have a critical design review at the end of the first phase of MSD II. This is typically a result of significant unanswered feasibility questions with no clear path to solution.
Expectations
- All team members present and prepared to report on team and individual status.
- All team MSD deliverables are complete and uploaded, and ready to be graded.
- Guide is present and prepared to evaluate all items included in the review.
- Review should take about an hour.
Status Review
Current state of the project
- Summarize expected performance vs. requirements (include snapshot of current requirements document here, along with a link to the live document.)
- Address any issues raised during your Detailed Design Review. These will generally fall into one of three categories
- Issues that have been addressed and the team is closing them out. (GREEN, team is ready to proceed to build and test)
- Issues that have not been addressed yet, but the team has a clear path to a solution. (YELLOW, team expects to be ready for build and test, and a Critical Design Review may be held in MSD II Week 2)
- Issues where the team has not been able to identify a solution or a clear path to a solution. (RED, team is not ready for build and test, and a Critical Design Review will be held in MSD II Week 2)
- Compare your current project plan/schedule to your original plan/schedule.
- Has the scope of your project changed?
- How and why did your schedule change?
- What have you learned from these changes?
The team decided that a on-demand concrete mixing system would be out of the scope of this project. Feasibility testing proved that such a subsystem would take too much time and development to allow for the successful completion of all the other subsystems. This pushed our schedule back about 3 weeks, which we think we can makeup during the Winter break. From this setback we learned we need to be very realistic in what we pursue and do a better job of developing subsystems in parallel. It is easy to get caught up in the testing of a particular subsystem but owners of other subsystems must make sure they are still keeping their work on track despite any additional workload that may come from testing.
- Review individual team member status.
- Did you deliver on your personal responsibilities?
- Did you use your MSD I plan effectively? Was it realistic? If not already addressed above, what did you learn from this and how have you applied this toward a meaningful and realistic MSD II plan?
Our original MSD I plan wasn't very realistic. Unfortunately we probably bit off more than we could chew by adding additional subsystems and functionality to the design, while understating how much work it would be to get the base subsystems working. So our initial scope was too large for the size of our team. We don't think this was all a waste though, as we uncovered some interesting future work that could be done for the printer. Specifically an on-demand mixing system certainly isn't outside the realm of possibility but would require more work than we can give it at this time. To make MSD II successful we have narrowed our scope and removed some subsystems from our design.
- Compare your current risk assessment to your original.
- Have you closed out your most important risks?
- Do you have remediation plans for remaining risks?
- Have any of these risks manifested themselves as problems?
- How did your risk assessment change? What can you learn from this?
Review your team's MSD II schedule (if not done during DDR)
- Your schedule demonstrates that you can deliver a functional prototype to your customer by your final phase demo.
- Your schedule incorporates lessons learned from your MSD I reflection.
- Spring-finish teams should include a vision for their Imagine RIT exhibit.
Plans for Break
Task Description
Start by
Duration
Complete by
Sequence
Impact
Time Required
Member
Duet configuration file
12/15 3 weeks 1/20 After gate review Allows the Duet to work with our motion system 6 hours
Anthony
Code for motion control 12/21 3 weeks 1/20 After gate review Interfacing between Duet and linear rails 10 hours Anthony Calibration system design 1/2 2 weeks 1/15 After MSD II starts Calibrating the printer on every start up is required 10 hours Anthony Contact stepper motor suppliers for torque curves 12/5 1.5 weeks 12/15 After stepper motor testing Necessary information for the stepper motor selection 2 hours + response time Derek Finalize stepper motor selection for Extruder 12/15 0.5 weeks 12/19 Need more information on stepper motors to make the selection Is necessary for an extruder design that can reliable extrude concrete 3 hours Derek Order stepper motor 12/19 4 weeks 1/9 Need the stepper motor before the extruder mount can be designed This will determine the final dimensions/weight of the extruder 1 hour + delivery time Derek/Nico Finalize stepper motor mounting design 1/09 1.5 weeks 1/20 This will be a critical portion of the final design This will determine the final dimensions/weight of the extruder 3 hours Derek Redesign internal bearings of extruder 12/10 4 weeks 1/7 Needs to be worked in parallel to the auger Is necessary for an extruder design that can reliable extrude concrete 6 hours Derek Update extruder auger design to be more efficient 12/10 4 weeks 1/7 Needs to be worked in parallel to the bearing design Is necessary for an extruder design that can reliable extrude concrete 6 hours Derek Update the nozzle design to be modular 1/7 3 weeks 1/21 Needs to be designed post completion of the auger and bearing update Is necessary for an extruder design that can reliable extrude concrete 6 hours Derek Design Bed attachment system 12/8 1 week 12/15 After gate review Allows bed to be level with extruder 3 hours Tyler Create CAD for design 12/8 2 weeks 12/22 After gate review Finalizes BOM for frame 12 hours Tyler Create BOM and purchase parts 12/15 1 week 12/29 After CAD completion Gets parts delivered 2 hours Tyler Parts shipping 12/20 3 weeks 1/25 After parts purchasing Delivery time 3 weeks Tyler Frame assembly 1/4 1 week 1/25 After parts arrive Allows for testing, not required to be done over break 1 week Tyler Check Lowes Inventory Status of Sakrete Type S 12/9 1 day 12/30 After gate review If product is hard to obtain material, team will have to focus on Type N as the final option 1 hour Meghan Keep Gantt Chart updated 12/8 6 weeks 1/25 This effort will continue throughout break Ensure team visibility of status of tasks for each member 6 hours Meghan Keep any test plans executed are uniformly documented and recorded in test plan file 12/8 6 weeks 1/25 Complete as new tests and data are developed. Provides team and stakeholders visibility of the test plans 10 hours Meghan Perform gravity concrete flow testing 1/9 1 week 1/16 After test parts arrive Tests feasibility of a gravity fed system from reservoir to extruder 6 hours Meghan Conduct Tubing Crush and Bend Radius Testing 12/14/2020 2 weeks 12/28/2020 After Gate Review This will determine the tubing material selection for the peristaltic pump allowing for preliminary design to be completed 10 hours Nicola Finalize Preliminary Pump Design 12/14/2020 12/27 01/05/2020 After Tubing Testing Allow for a manufacturing strategy to be created and begun 15 hours Nicola Test Pump with water Once parts are acquired 1 week Start of MSD II After Pump Design is finalized Better understand how pump functions 10 hours Nicola Design Hopper 12/28/2020 3 weeks 1/14/2020 Once tubing material for pump is selected A Reservoir system to store mixed concrete prior to printer using is necessary for the functioning of the printer 15 hours Nicola Order Pump Materials 12/272020 1 week 1/20/2020 Once preliminary design is complete Allow for system testing at the beginning of MSD II 2 hours Nicola Order Hopper Materials 1/14/2020 1 week 1/20/2020 After Preliminary design is complete Allow for system testing at the beginning of MSD II 2 hours Nicola
Publish Hopper Drawings 1/14/2021 1 week 01/25/2021 Once preliminary design is complete Allow for a manufacturing strategy to be created and begun 5 hours Nicola Manufacture Hopper Once Drawing are complete 1 week 02/01/2021 Once Drawings are complete and material is recieved Allow for system testing at the beginning of MSD II 15 hours Nicola Manufacture Pump Once Drawing are complete 1 week 02/01/2021 Once Drawings are complete and material is recieved Allow for system testing at the beginning of MSD II 15 hours Nicola Research Duet Firmware (Reprap) and Gcode 12/9 5 weeks 1/20 Needed for next phase Will give the team the knowledge needed to program the printer 5 hours each Everyone
Plans for Next PhaseBetween now and the end of the semester the team hopes to complete the peristaltic pump design as well as finalize some bills of materials. We do not expect to do much more testing or prototyping for the rest of the semester. In order to prepare for MSD II some subsystems will be worked on over the 6 week winter break. Anthony will be working on the electrical subsystem. As mentioned before, the Duet needs custom configuration files for the connected motors and since we will be having a new extruder stepper motor, we will need new configuration files. In addition, certain minor subsystems such as the user interface and the calibration system can also begin to get designed since we now have a good idea of the direction we are going with the project. Wiring diagrams can also begin to be drawn up but subject to change; they will not be needed until the frame is assembled. Any related code will be researched and by the start of next semester we will have a solid understanding of the scope of the Duet within this project.
As a team, we would like to be prepared for the start of the spring semester term. This includes preparation for MSD II and any left over tasks from MSD I. Below are individual tasks the team will work on to help our team achieve these goals.
Task Description
Start by
Duration
Complete by
Sequence
Impact
Time Required
Member
Task Description
Start by
Duration
Complete by
Sequence
Impact
Time Required
Member
Wiring diagrams February After MSD II starts and frame is set up Connects everything to the Duet 5 hours Anthony Calibration system design February After MSD II starts Calibrating the printer on every start up is required 2 hrs/week Anthony User interface system February After MSD II starts Provides information to user 5 hours Anthony Determine extrusion rate and linear speed of extruder 1/25 1 week 2/1 After MSD II starts and extruder design is complete This will be necessary to define printing parameters and extruder capabilities 4 hours Derek Test extruder on the printer frame 2/1 2 weeks 2/14 XY frame and extruder needs to be complete This is a critical step in implementing this subsystem into the printer 4 hours Derek Test Pump and hopper together with concrete 02/01/2021 1 week 02/08/2021 After parts are manufactured Ensure pump functions as expected and any minor tweaks that need to be made can be made 8 hours Nicola Calibrate pump rate with extrusion rate 02/08/2021 4 days 02/11/2020 Once pump and hopper are tested together and extrusion rate is better understood Allow for pump to be properly integrated with full system 8 hours Nicola Test Hopper, Pump, and extruder together 02/12/2021 1 week 02/19/2021 Once Pump is calibrated to extruder and software to control pump is written Checks the three systems together before adding in the variable of motion 8 hours Nicola Test Hopper, Pump, extruder, and linear motion together 02/20/2021 1 week 02/27/2021 once pump is tested with the extruder Tests that all systems are working in tandem 8 hours Nicola Revise test plans from decisions made over break First Class Back After work designated for break is complete These may need updated dependent of the individual task completed over break. 1 hour Meghan Update Risk Assessment Status End of Phase 5 After Risks are raised or mitigated Rising risks must be addressed as a team and documented the corrective action taken. 3 hours Meghan Collect data for benchmark testing End of Phase 5 Once design is finalized This will provide a benchmark for the expected and desired engineering requirements to me tested against. 20 hours Everyone Assemble frame February Once parts come in Allows testing of XYZ axis and integration of other subsystems 2 hours Tyler Test X, Y, Z motion February 14th After frame is assembled Completes engineering requirement 4 hours Tyler, Anthony Monitor for wear End of project After frame is assembled Ensure design is rigid and rugged enough for continued use Continuous Tyler Assist in design and assembly where needed End of project After frame is mostly finished Since the frame is mostly done I am more free to assist in other topic and setup Continuous Tyler
Team Self-Critique
Deliverables Checklist and Website Status
- All documents must be uploaded to your website in advance of the Gate Review.
- The team should not use gate review time to conduct a detailed examination of specific deliverables unless related to discussion items in the status review.
MSD II: Project close-out
- Use this space to organize information for your review. Key elements are listed here
Expectations
- All team members present and prepared to report on team and individual status.
- All team MSD deliverables are complete and uploaded, and ready to be graded.
- Guide is present and prepared to evaluate all items included in the review.
- Review should take about an hour.
Status Review
Current state of the project
- Summarize actual performance vs. requirements (include snapshot of current requirements document here, along with a link to the live document.).
- Which requirements were unmet, and why?
- How robust is your final design?
- Did you meet your project budget?
- What was your customer's assessment of the work you delivered to them? Were they satisfied?
- Compare your current project plan/schedule to your original plan/schedule.
- Did the scope of your project change during MSD II?
- How and why did your schedule change during MSD II?
- What have you learned from these changes that you can apply to future projects?
- Review individual team member status.
- Did you deliver on your personal responsibilities?
- Did you use your MSD II plan effectively? Was it realistic? If not already addressed above, what did you learn from this and how can you apply it to future projects?
- Review your current risk assessment and problem solving status.
- Have you closed out your most important risks?
- Were there risks that you did not anticipate? If so, what do you think the reason is?
- Did any anticipated risks manifest themselves as problems?
- How did you use your problem solving process during the semester?
Deliverables Checklist and Website Status
- All documents must be uploaded to your website in advance of the Gate Review.
- The team should not use gate review time to conduct a detailed examination of specific deliverables unless related to discussion items in the status review.
- Is prototype hand-off complete, is the team's workspace cleaned up, and have all tools been returned?
Lessons learned, etc.
- Does the team have any other lessons learned that were not addressed above?
- What advice would you give to future teams?