RIT will permanently shut down the RIT Wiki (Confluence wiki) on February 2, 2024. Review the Wiki Shut Down Overview for information on alternative tools, exporting content from the wiki, and other FAQs.
Details
Date: Monday, November 02, 2020
Time: 10:00-11:15 AM
Location: https://rit.zoom.us/j/99051711329
Agenda: https://docs.google.com/document/d/1f4e4ArrjVB0VzxWKCl7PzDlWlBZcjx174-x8i8go-tc/edit?usp=sharing
Slide deck: https://docs.google.com/presentation/d/1ynjWxyF3E__UAZ79HJFozY0SFZQN6SHb1O73QpL2czE/edit?usp=sharing
Project overview document: https://docs.google.com/document/d/1VLp_J5oBDFqTUjXiyGni8UUL6vyUU9oyLmJ4bCD_UBw/edit?usp=sharing
Attendees
P21677 team members
- Felix Chamberland (Systems Engineer - Mechanical Support)
- Ramsey Doolittle (Communications)
- Diana Kulawiec (Project Manager)
- Emma Kurz (Facilitator)
- Hayley Miller (Systems Engineer - Bioprinting)
- Mark Truskinovsky (Systems Engineer - Software, Purchasing)
- Faculty guide
- Customer
- Vinay Abhyankar
Goals
- Share the progress that has been made and the insight that has been acquired as a result of the feasibility testing items that have been acted on since the previous review.
- Reiterate prioritized feasibility items and assignments.
- Discuss the prioritization of first assessing UV crosslinking feasibility.
- Safety specifications
- Implementation
- Discuss the prioritization of first assessing syringe pump design and implementation.
- Assembly
- Modification of design for specific application
- Mounting
- Software-based control
Agenda and discussion notes
Time | Item | Who | Notes |
|---|---|---|---|
| 3 min | Refresher | Diana Kulawiec | |
| 2 min | Team vision | Ramsey Doolittle | |
| 1 min | Feasibility overview | Hayley Miller | |
| 3 min | UV crosslinking overview | Hayley Miller | |
| 7 min | UV crosslinking safety | Hayley Miller | |
2 min | LED implementation | Félix Chamberland | |
| 4 min | UV testing conditions | Emma Kurz | |
| 3 min | UV crosslinking evaluation parameters | Diana Kulawiec | |
| 4 min | Syringe pump overview | Ramsey Doolittle | |
| 7 min | Syringe pump CAD design details | Ramsey Doolittle | |
| 4 min | UV attachment relative to syringe pump | Félix Chamberland | |
| 4 min | Syringe pump software overview | Mark Truskinovsky | |
| 4 min | Syringe pump next steps | Mark Truskinovsky | |
| 3 min | Feasibility task 4 - printing parameters | Mark Truskinovsky | |
| 3 min | Feasibility task 5 - printhead weight | Emma Kurz | |
| 2 min | Feasibility task 6 - Syringe size/nozzle | Diana Kulawiec | |
| 3 min | Updates on system-level flow chart | Félix Chamberland | |
| 4 min | Bill of materials (BOM) | Mark Truskinovsky | |
| 2 min | Risk assessment | Mark Truskinovsky | |
| 2 min | Plans for next phase | Emma Kurz |