| Item | Resources Required Needed to Start | Expected Time to Complete | Individual Responsible | Start Date | Due Date | Notes |
|---|---|---|---|---|---|---|
| Carbon Fiber Body tube for Upper tube | Ordered shrink tape, and releasing agent | 1-2 weeks | Pat | October 24 | working through difficulties, we do have a ID | |
| Carbon Fiber Tube Testing | 1 week | MSD | ||||
| Nose Cone modeling | Foam or MDF, Prepreg Carbon fiber sheets | 1 week | Matt | October 24 | October 31 | Cam is done ETA Nov 7 |
| Arming Switches | Jim | November 20 | ||||
| Avionics Hardware | 1 week | Joe | October 31 | ETA software | ||
| Camera Hardware | Will | ? | Nov 14 | |||
| Avionics Software | 3 weeks | Joy | October 31 | ETA Nov 14 | ||
| Avionics Bay manufacturing | 1 week | Aubrey | October 24 | November 14 | avionics sled, camera holes, avionics bulkhead | |
| Carbon fiber Booster and Boat tail manufacturing | Pat | October 24 | November 7 | |||
| Fin Can manufacturing | PET G, Fin Material | Carl | October 24 | November 14 | ||
| Motor Retainer manufacturing | Aluminum Stock | Kevin | November 7 | November 20 | ||
| Fin | Carbon fiber plate | 1 week | January 28 | Feb 5 | ||
| Full Assembly | November 20 | |||||
| Deployment testing | ||||||
| Cutting Jig | Matt | End of November |